General Alert:

Final OGPA surfacing is now completed with linemarking to be completed Thursday 19 November.

Final surfacing is being completed at London Road, with stop/go operation in place for a period of time this week.

Barrier construction will also be completed closing the gap between the northbound and southbound lanes at Cornish Street.  Cornish Street exit onto SH2 will also be closed on Friday.

Thursday 19 November

  • 9.00am – 7.00pm: Southbound lane closure from Maungaraki to Petone Overbridge.
  • 7.00am – 4.00pm: Northbound lane closure from Petone Overbridge to Maungaraki.
  • 8.00am – 4.00pm Stop/Go on Pito-One Road adjacent the soldier pile wall for pavement construction.
  • 7.00pm – 7.00am NIGHT WORKS: Northbound lane closure Petone Overbridge to Korokoro Overbridge (barrier construction and linemarking).
  • 7.00pm – 5.00am NIGHT WORKS: Southbound lane closure Petone Overbridge to Korokoro Overbridge (barrier construction and linemarking).

Friday 20 November

  • All temporary traffic management to be removed from the SH2 alignment.
  • 8.00am – 4.00pm Stop/Go on Pito-One Road adjacent the soldier pile wall for pavement construction.

Saturday 21 November

  • 7.00am – 12.00pm Stop/Go Pito-One Road adjacent the soldier pile wall.
  • Site to be monitored with maintenance carried out as necessary.

Sunday 22 November

  • No scheduled closures during the day.
  • Site to be monitored with maintenance carried out as necessary.
  • Tentative 7.00pm – 7.00am NIGHT WORKS: Northbound lane closure Petone Overbridge to Korokoro Overbridge (barrier construction).
  • Tentative 7.00pm – 5.00am NIGHT WORKS: Southbound lane closure Petone Overbridge to Korokoro Overbridge (barrier construction).

Monday 23 November

  • 9.00am – 7.00pm: Southbound lane closure from Maungaraki to Petone Overbridge if required.
  • 7.00am – 4.00pm: Northbound lane closure from Petone Overbridge to Maungaraki if required.
  • 7.00am – 4.00pm Stop/Go on Pito-One Road adjacent the soldier pile wall for final surfacing if required.
  • Tentative 7.00pm – 7.00am NIGHT WORKS: Northbound lane closure Petone Overbridge to Korokoro Overbridge (barrier construction).
  • Tentative 7.00pm – 5.00am NIGHT WORKS: Southbound lane closure Petone Overbridge to Korokoro Overbridge (barrier construction).

Tuesday 24 November

  • 9.00am – 7.00pm: Southbound lane closure from Maungaraki to Petone Overbridge if required.
  • 7.00am – 4.00pm: Northbound lane closure from Petone Overbridge to Maungaraki if required.
  • 7.00am – 4.00pm Stop/Go on Pito-One Road adjacent the soldier pile wall for final surfacing if required.
  • Tentative 7.00pm – 7.00am NIGHT WORKS: Northbound lane closure Petone Overbridge to Korokoro Overbridge (barrier construction).
  • Tentative 7.00pm – 5.00am NIGHT WORKS: Southbound lane closure Petone Overbridge to Korokoro Overbridge (barrier construction).

Wednesday 25 November

  • 9.00am – 7.00pm: Southbound lane closure from Maungaraki to Petone Overbridge if required.
  • 7.00am – 4.00pm: Northbound lane closure from Petone Overbridge to Maungaraki if required.
  • Tentative 7.00pm – 7.00am NIGHT WORKS: Northbound lane closure Petone Overbridge to Korokoro Overbridge (barrier construction).
  • Tentative 7.00pm – 5.00am NIGHT WORKS: Southbound lane closure Petone Overbridge to Korokoro Overbridge (barrier construction).

Thursday 26 November

  • 9.00am – 7.00pm: Southbound lane closure from Maungaraki to Petone Overbridge if required.
  • 7.00am – 4.00pm: Northbound lane closure from Petone Overbridge to Maungaraki if required.
  • Tentative 7.00pm – 7.00am NIGHT WORKS: Northbound lane closure Petone Overbridge to Korokoro Overbridge (barrier construction).
  • Tentative 7.00pm – 5.00am NIGHT WORKS: Southbound lane closure Petone Overbridge to Korokoro Overbridge (barrier construction).

Friday 27 November

  • 9.00am – 7.00pm: Southbound lane closure from Maungaraki to Petone Overbridge if required.
  • 7.00am – 4.00pm: Northbound lane closure from Petone Overbridge to Maungaraki if required.