Weekly Traffic Report
Special Alert:
Please refer to the Wednesday 23 July for details of traffic signal modification at Korokoro and Bridge Beam lifts on Hutt Road.
General Alert:
There are major alterations at Korokoro Intersection. Take care, and follow the signs for directions to and from Korokoro, Petone and SH2.
Thursday 17 July
- 9.00am – 6.00pm: Southbound lane closure from Maungaraki to Petone Overbridge for stormwater system installation and bridge construction.
- 8.00am – 3.00pm: Northbound lane from Cornish Street to Priests Ave for installation of underground services.
- 9.00am – 4.00pm: Southbound shoulder closures, speed restrictions, and reduced car parking on Hutt Road from Beaumont Ave to Wakefield St for property modifications and stormwater installation.
Friday 18 July
- 9.00am – 6.00pm: Southbound lane closure from Maungaraki to Petone Overbridge for stormwater system installation and bridge construction.
- 9.00am – 4.00pm: Southbound shoulder closures, speed restrictions, and reduced car parking on Hutt Road from Beaumont Ave to Wakefield St for property modifications.
Saturday 19 July
Sunday 20 July
Monday 21 July
- 9.00am – 6.00pm: Southbound lane closure from Maungaraki to Petone Overbridge for stormwater system installation and bridge construction.
- 9.00am – 4.00pm: Southbound shoulder closures, speed restrictions, and reduced car parking on Hutt Road from Beaumont Ave to Wakefield St for property modifications.
Tuesday 22 July
- 8.00am – 3.00pm: Northbound lane closure at Korokoro for traffic signal modification.
- 9.00am – 6.00pm: Southbound lane closure from Maungaraki to Petone Overbridge for stormwater system installation and bridge construction.
- 9.00am – 4.00pm: Southbound shoulder closures, speed restrictions, and reduced car parking on Hutt Road from Beaumont Ave to Wakefield St for property modifications.
Wednesday 23 July
- 11.00am – 2.00pm: Traffic signals at Korokoro switched off for signal modification. Manual traffic control in place alongside a lane closure and speed restriction to 30km.
- 8.00am – 3.00pm: Northbound lane closure at Korokoro for traffic signal modification.
- 9.00am – 6.00pm: Southbound lane closure from Maungaraki to Petone Overbridge for bridge construction, traffic signal modification, and stormwater installation.
- 9.00am – 4.00pm: Southbound shoulder closures, speed restrictions, and reduced car parking on Hutt Road from Beaumont Ave to Wakefield St for property modifications.
Thursday 24 July
- 9.00am – 7.00pm: Southbound lane closure from Maungaraki to Petone Overbridge for installation of underground services, installation of stormwater system, and bridge construction
- 8.00am – 4.00pm: Northbound lane closure from Petone Overbridge to Maungaraki for installation of underground services, installation of stormwater system, and bridge construction
- 9.00am – 7.00pm: Shoulder closures, speed restrictions, and reduced car parking on Hutt Road from Beaumont Ave to Wakefield St for property modifications and crane set up.
- 7.00pm – 6.00am Friday: Hutt Road closed for bridge beam lift. Detour via Wakefield St and Beamount Ave.
- 7.00pm – 6.00am Friday: Northbound rolling blocks along SH2 from Ngaraunga Interchange to Hutt Road to allow safe transport of bridge beams.
Friday 25 July
- 9.00am – 7.00pm: Southbound lane closure from Maungaraki to Petone Overbridge for installation of underground services, installation of stormwater system, and bridge construction
- 8.00am – 4.00pm: Northbound lane closure from Petone Overbridge to Maungaraki for installation of underground services, installation of stormwater system, and bridge construction
- 9.00am – 4.00pm: Shoulder closures, speed restrictions, and reduced car parking on Hutt Road from Beaumont Ave to Wakefield St for property modifications.
Saturday 26 July
Sunday 27 July