Project Details
Warkworth Stage 1 |
|
| SH1
|
|
| Warkworth, Rodney, Auckland
|
|
![]() |
|
| Purpose: | Transit's Statutory Objective under section 70 of the Land Transport Management Act 2003 is:
Consistent with this are the project objectives for Warkworth Stage 1 to:
The result of collaboration between Transit and Rodney District Council, the integrated state highway and local road improvements will cater for the expected growth and development in the Rodney region through to 2021 and ease evening peak and seasonal congestion in Warkworth. |
|---|---|
| EstimatedCost: | $5-20m* |
| Start Date: | 2008 planned construction start |
| End Date: | 2012 planned construction finish |
| Location: | Warkworth, Rodney, Auckland |
| Engineering Features: | The proposed works are as follows:
|
| Interesting Facts: | The work will take place in stages, over approximately the next seven years and has been designed to support and match pace with development planned in Rodney, as detailed in Rodney District Council's Warkworth Structure Plan. Strategic coordination of the roading improvements with new developments means that additional traffic generated by those developments will be actively managed. |
| Other: | *Under a cost sharing agreement meeting Land Transport New Zealand's funding criteria - Transit will implement the state highway components and Rodney District Council will be responsible for constructing the Western Collector road, and funding the local roading elements. Website |
| More Information: | Mieszko Iwaskow |
| PDFFile: | Download |