Project Details

Tahuna Road Roundabout


SH27
The intersection of Tahuna Road and SH27, approximately 30kms south of the SH2/SH27 intersection at Mangatarata and 44kms north of Matamata.
Purpose: To improve safety at the intersection of Tahuna Road and SH27 by replacing the existing staggered tee intersection with a roundabout.
EstimatedCost: $3.3M*
Start Date: Construction is expected to start late May 2009
End Date: Construction is expected to be completed by late 2010
Location: The intersection of Tahuna Road and SH27, approximately 30kms south of the SH2/SH27 intersection at Mangatarata and 44kms north of Matamata.
Engineering Features: The first stage of works involves placing excess fill in the new embankment areas to encourage the underlying soft ground to settle. This is expected to take six months. Once the ground has settled the excess fill will be used to form new fill slopes and construction of the roundabout will start.

Interesting Facts: Tahuna Road is a local road administered by Matamata-Piako District Council. Both roads carry high levels of heavy vehicles (18% compared to the national average of around 10%).
Other: *Transit New Zealandâ??s 10-year State Highway Plan and Forecast for 2007/08 to 2016/17.
More Information: Alison Keehan