Eureka Bend Reinstatement Project


SH60
100m stretch of road on Takaka Hill known as Eureka Bend
Purpose: To restore the highway to full capacity following a slip in 2007 that reduced the highway to one lane.
EstimatedCost: $2.4m
Start Date: February 2009
End Date: Mid 2009
Location: 100m stretch of road on Takaka Hill known as Eureka Bend
Engineering Features: Involves the removal of any unstable earth on the Takaka Hill where a temporary Bailey Bridge was established following the slip. The remaining hillside will then be reinforced using a special slope stabilisation technique known as mechanically stabilised earth (MSE)
More Information: Andree Kai Fong