Hayward's Interchange
|
2/58
|
SH2 intersection with SH58 (Hayward's Hill) Wellington
|
| Purpose: | To separate conflicting traffic flows |
| EstimatedCost:
| $40 million |
| Start Date:
| Design and designation due for completion mid 2010 |
| End Date:
| tbc |
| Location:
| SH2 intersection with SH58 (Hayward's Hill) Wellington |
| Engineering Features:
| Proposed: A grade separated interchange (elevated roundabout) at the intersection of SH2 and SH58; a new carpark with approximately 40 spaces will replace the existing informal carpark; replacement of the existing underpass with a footbridge across SH2 to Manor Park Road and Manor Park Station. |
| Interesting Facts:
| The layout of the grade separated interchange is similar to the new Dowse Interchange on SH2 but there will be fewer retaining walls.
|
| Other:
|
|
| More Information:
| Andree Kai Fong |