Construction Updates

July 2007

June 2007

May 2007

April 2007

March 2007

February 2007

January 2007

December 2006

November 2006

October 2006

September 2006

August 2006

July 2006

June 2006

May 2006

April 2006

March 2006

February 2006

January 2006

December 2005

November 2005

October 2005

September 2005

August 2005

July 2005

June 2005

May 2005

April 2005

March 2005

February 2005

January 2005

December 2004

November 2004

October 2004

September 2004

 

September 2006

  • Last concrete wall pour in the trough structure
  • Pavement constructed between trough structure and Terrace Tunnel
  • Buckle intersection changes commence

August 2006

  • Last concrete floor pour in the trough structure
  • Works in Aro Park commence to complete the Te Aro stormwater culvert

^ Back to top

July 2006

  • First pedestrian shelters installed
  • Project team is awarded the “Best Project : Large” award for being “a premium team delivering Project Excellence”.

June 2006

  • 272 Willis Street building relocated from temporary site to permanent site
  • Landscaping works commence in Tonks Grove

^ Back to top

May 2006

  • Archaeologists are able to date the earliest bottles found on the site as early to mid 1860s
  • The first pre-cast panels for the acoustic barrier are installed at the top of the trench
  • Restoration works in Tonks Grove complete

April 2006

  • Road works for the re-alignment of Victoria Street commence
  • Landscaping and urban design works in Willis Street area commence

^ Back to top

March 2006

  • Excavation and soil nail installation between Vivian Street and Willis Street complete
  • Footpath/cycleway works in Buckle Street complete
  • Restoration works on 286 Willis Street (former Bar Bodega) commence
  • Urban design works on new alignment next to Arthur Street commence

February 2006

  • First structural prop installed across the trench
  • New sewer main in Cuba Street completed
  • 272 Cuba Street, the former Freedom Shop, relocated to permanent position

^ Back to top

January 2006

  • Renovation of ex-Avonside building (215 Vivian St) completed
  • Restoration works start on ex-12 Tonks and ex-14 Kensington Street buildings
  • Te Aro drain chamber in Willis Street yard completed

December 2005

  • Restoration completed on 282 and 284 Willis Street buildings
  • First pedestrian shelter installed
  • Buckle Street cycleway and footpath completed between Cambridge/Kent and Tory Streets
  • Vivian Street bridge open to the public

^ Back to top

November 2005

  • First tree planted on corner of Tory and Buckle Streets
  • Vivian Street bridge beams delivered to site and placed
  • Last heritage building relocated (319 Willis Street).

October 2005

  • 13 Tonks relocated
  • 272 Cuba temporarily relocated
  • HPT onsite investigations completed
  • Palmer Street road and footpath sealed

^ Back to top

September 2005

  • 30 Arthur Street relocated
  • Aro Preschool moved temporarily to Buller Street
  • Last building demolished
  • Te Aro s/w completed in Palmer Street to Aro Park.

August 2005

  • New Tonks Avenue heritage buildings relocated.
  • Buckle Street cycleway and footpath works commenced.

^ Back to top

July 2005

  • Te Aro culvert installation commences in Palmer Street

June 2005

  • Cuba Street heritage buildings commence relocation
  • Bodega heritage building relocated.

^ Back to top

May 2005

  • Vivian Street diverted

April 2005

  • Te Aro culvert installation begins in Arthur Street
  • Motorway widened between Willis and Ghuznee Streets.

^ Back to top

March 2005

  • Earthworks for the trench structure commence
  • Visitors' Centre opens at 319A Willis Street

February 2005

  • First heritage building relocated (215 Vivian Street)
  • Archaeological Open Days

^ Back to top

January 2005 - Construction commences

  • 26 Archaeologists investigate Kensington-Taranaki
  • Buildings started to be demolished
  • Areas cleared

^ Back to top

December 2004 – Soil nail testing commences

November 2004 – Site preparation work commences

October 2004 – Start consent compliance management plans

September 2004 – Physical works tender awarded