September 2006
- Last concrete wall pour in the trough structure
- Pavement constructed between trough structure and Terrace Tunnel
- Buckle intersection changes commence
August 2006
- Last concrete floor pour in the trough structure
- Works in Aro Park commence to complete the Te Aro stormwater culvert
^ Back to top
July 2006
- First pedestrian shelters installed
- Project team is awarded the “Best Project : Large” award for being “a premium team delivering Project Excellence”.
June 2006
- 272 Willis Street building relocated from temporary site to permanent site
- Landscaping works commence in Tonks Grove
^ Back to top
May 2006
- Archaeologists are able to date the earliest bottles found on the site as early to mid 1860s
- The first pre-cast panels for the acoustic barrier are installed at the top of the trench
- Restoration works in Tonks Grove complete
April 2006
- Road works for the re-alignment of Victoria Street commence
- Landscaping and urban design works in Willis Street area commence
^ Back to top
March 2006
- Excavation and soil nail installation between Vivian Street and Willis Street complete
- Footpath/cycleway works in Buckle Street complete
- Restoration works on 286 Willis Street (former Bar Bodega) commence
- Urban design works on new alignment next to Arthur Street commence
February 2006
- First structural prop installed across the trench
- New sewer main in Cuba Street completed
- 272 Cuba Street, the former Freedom Shop, relocated to permanent position
^ Back to top
January 2006
- Renovation of ex-Avonside building (215 Vivian St) completed
- Restoration works start on ex-12 Tonks and ex-14 Kensington Street buildings
- Te Aro drain chamber in Willis Street yard completed
December 2005
- Restoration completed on 282 and 284 Willis Street buildings
- First pedestrian shelter installed
- Buckle Street cycleway and footpath completed between Cambridge/Kent and Tory Streets
- Vivian Street bridge open to the public
^ Back to top
November 2005
- First tree planted on corner of Tory and Buckle Streets
- Vivian Street bridge beams delivered to site and placed
- Last heritage building relocated (319 Willis Street).
October 2005
- 13 Tonks relocated
- 272 Cuba temporarily relocated
- HPT onsite investigations completed
- Palmer Street road and footpath sealed
^ Back to top
September 2005
- 30 Arthur Street relocated
- Aro Preschool moved temporarily to Buller Street
- Last building demolished
- Te Aro s/w completed in Palmer Street to Aro Park.
August 2005
- New Tonks Avenue heritage buildings relocated.
- Buckle Street cycleway and footpath works commenced.
^ Back to top
July 2005
- Te Aro culvert installation commences in Palmer Street
June 2005
- Cuba Street heritage buildings commence relocation
- Bodega heritage building relocated.
^ Back to top
May 2005
April 2005
- Te Aro culvert installation begins in Arthur Street
- Motorway widened between Willis and Ghuznee Streets.
^ Back to top
March 2005
- Earthworks for the trench structure commence
- Visitors' Centre opens at 319A Willis Street
February 2005
- First heritage building relocated (215 Vivian Street)
- Archaeological Open Days
^ Back to top
January 2005 - Construction commences
- 26 Archaeologists investigate Kensington-Taranaki
- Buildings started to be demolished
- Areas cleared
^ Back to top
December 2004 – Soil nail testing commences
November 2004 – Site preparation work commences
October 2004 – Start consent compliance management plans
September 2004 – Physical works tender awarded